Iran
has acted to cut its most sensitive nuclear stockpile by nearly 75
percent in implementing a landmark pact with world powers, but a planned
facility it will need to fulfill the six-month deal has been delayed, a
U.N. report showed on Thursday. The monthly update by the International Atomic Energy Agency , which has a pivotal role in verifying that Iran
is living up to its part of the accord, made clear that Iran so far is
undertaking the agreed steps to curb its nuclear program. As
a result, it is gradually gaining access to some previously blocked
overseas funds. In Washington, the State Department said the United
States has taken steps to release a $450 million installment of frozen
Iranian funds following the issuance of the report. In
addition, Japan has made two more payments totaling $1 billion to Iran
for crude imports, two sources with knowledge of the transactions said. Under
the breakthrough agreement that took effect on January 20, Iran halted
some aspects of its nuclear program in exchange for a limited easing of
international sanctions that have laid low the major oil producer's economy. It
was designed to buy time for negotiations on a final, long-term
settlement of the decade-old dispute over nuclear activities that Iran
says are peaceful but the West says may be covertly directed toward
developing an atomic bomb capability. Those
talks - made possible by the election last year of a pragmatist, Hassan
Rouhani, as Iranian president after years of confrontation with the
West under his hardline predecessor, Mahmoud Ahmadinejad - got under way
in February and are aimed at reaching an agreement by July 20.
Washington has not ruled out military action against Iran if diplomacy
were to fail. The IAEA
update showed that Iran had - as stipulated by the November 24 agreement
with the United States, France, Germany, Britain, China and Russia -
diluted half of its higher-grade enriched uranium reserve to a fissile
content less prone to bomb proliferation. One of the payments from
Japan, of $450 million on April 15, hinged on Iran meeting this target. Tehran
has also continued to convert the other half of its stock of uranium
gas refined to a 20 percent fissile purity - a relatively short
technical step from 90 percent weapons-grade material - into oxide for
making reactor fuel. Altogether,
Iran has in the last three months either diluted or fed into the
conversion process a total of almost 155 kg (340 pounds) of its
higher-grade uranium gas, which amounted to 209 kg when the deal came
into force, a bit less than the roughly 250 kg experts say would be
needed for a bomb, if refined more. This
will be seen as a positive development by Western states since it
lengthens the time Iran would need for any effort to amass enough
fissile material for the core of a nuclear weapon. The Islamic Republic
has insisted it is refining uranium to fuel only nuclear reactors, not
bombs. U.S. State
Department spokeswoman Marie Harf said "all sides have kept the
commitments made" under the November 24 agreement. Harf said "as Iran
remains in line with its commitments," the United States and its
international partners "will continue to uphold our commitments as
well." NUCLEAR FACILITY DELAY The
IAEA report also pointed to a new delay in Iran's construction of a
plant designed to turn low-enriched uranium gas (LEU) into an oxide
powder that is not suitable for further processing into highly enriched
bomb-grade uranium. Iran
told the IAEA last month that the site would be commissioned on April 9.
But Thursday's update by the U.N. nuclear watchdog said the
commissioning had been put off, without giving any reason. However,
"Iran has indicated to the agency that this will not have an adverse
impact on the implementation of (its) undertaking" to convert the
uranium gas, the agency said. The
delay means that Iran's LEU stockpile - which it agreed to limit under
the Geneva pact - is almost certainly continuing to increase for the
time being, simply because its production of the material has not
stopped, unlike that of the 20 percent uranium gas. Western
diplomats said earlier that this matter was of no immediate consequence
as Iran's commitment concerns the size of the reserve towards the end
of the deal, in late July, meaning it has time both to complete the site
and convert enough LEU. But
they also say that the Islamic Republic's progress in building the
conversion line will be closely monitored. The longer it takes to
complete it, the more material Iran will have to process to meet the
target in three months' time. "The
delay is not long enough to raise a red flag," said Iran expert Ali
Vaez at the International Crisis Group think-tank. Once the plant is "up
and running, Iran could retroactively convert any excess material to
oxide", he said. Mark
Hibbs of the Carnegie Endowment think-tank said he believed there may be
a technical reason for the postponement. "It is hard to believe that
Iran would not meet that commitment it has made on the conversion in
good faith," he said. If
it complies with the interim deal, Iran will get a total of $4.2 billion
in revenues long frozen oversees, in eight installments over the
January-July period. Including Japan's latest payments, it has received
$2.55 billion. South Korea, another importer of Iranian oil, has made
one payment.
Iran cuts sensitive nuclear stockpile, key plant delayed: IAEA
Reuters
Comments About This Article
Please fill the fields below.